PHYSICAL PLAN EXPANSION CHRONOLOGY |
|
| The physical plant expansion component to the capital campaign |
| |
adds 3 floors to the LINK Building, which adds 9 new classrooms/labs and several new offices
- enlarges the Fieldhouse outward with a new girls' locker room and aerobics room
- adds a building west of the new gym for hospitality, reception and waiting
- moves the Admissions Office to the existing Maintenance Area
- turns the current Girls' Locker Room into a new Maintenance Area
- expands the Library into the Laundry Room/G08
- enhances the aesthetic appeal of Fenwick's southern exposure
|
| Construction work will begin in 2007 around Easter and finish around Christmas |
| |
| Phase I: Easter to Memorial Day |
| |
- Existing Girls' Locker Room becomes a new Maintenance Area
- Existing Maintenance Area gutted for reconfiguration into new Admissions area
- Library Closed
- LINK Doors closed and off limits. All pedestrian entrance/egress will be from Washington Boulevard and Scoville Avenue
- Faculty parking available in Fenwick lot.
|
| |
| Phase II: Memorial Day to August 15, 2007 |
|
- The steel infrastructure to expanded LINK erected.
- The Fieldhouse will expand.
- New Reception Area constructed. External walls will be built.
- The LINK Doors remain closed.
- Most of the parking lot will be given over to construction. We will have an auxiliary parking lot at Madison Street and Oak Park Avenue
- NO PEDESTRIAN TRAFFIC ALLOWED IN THE LINK CORRIDORS.
|
| |
| Phase III: August 15, 2007 to Thanksgiving |
| |
- Internal work completed.
- The LINK Doors remain closed.
- The buses may go out onto Washington Boulevard.
- Expanded Library RE-OPENED.
- Most parking restored.
|
| |
| Phase IV: Thanksgiving to Christmas |
| |
- LINK Doors back into service.
- The new Admissions area in operation.
- New Reception Area now main entrance to the School.
- New Aerobics Room and new Girls' Locker Room available
- Fenwick Parking lot back in full function.
|
| |
| Phase V: Christmas 2007 to Martin Luther King Day 2008 |
| |
- Final touches completed on the nine new classrooms in the LINK
|
|